Written by Pete and Pete
|
Thursday, 29 October 2009 |
Pete and Pete's progress report:
October 09
We are still banging away on Kawakawa Bay track been getting a bit of a soaking at times but a bonus is the track packs down fast We are up to the main steam crossing working our way out of the gully. This will bypass the stairs once we have shifted the bridge.
September 09
With DoC we have started upgrading the Kawakawa Bay track. The grades will be more like W2K so the whole track is able to be ridden but at the same time we are hoping we can retain the character of the track going through the rock areas and the stream crossings.
|